Hector Airport announces the beginning of the 2008 construction project expanding the cargo ramp on the north side of the airport. The first half of the project advertised for bid earlier this month, and Northern Improvement won with the lowest bid of just under $1.6 million. Other bids reached nearly $2.5 million.
In addition to DHL, Hector Airport has many feeder cargo companies which operate daily air service for other air cargo companies. The airport had hoped to accomplish more in the first year of this project; however, federal funding in the form of Airport Improvement Program (AIP) money was reduced by 25 percent nationwide for the fiscal year 2008. This money is normally used to fund up to 90 percent of federally approved projects. Copyright © 2012 Municipal Airport Authority, All Rights Reserved. |