Q Construction began in October 2006 and completed in September 2008. Q $14.9M total cost (including EDS room and Coffee Bar project) Q 42,000 ft2 added with west and north addition (one gate and one baggage claim) Q 118,000 ft2 total terminal space - five (5) gates and three (3) baggage claims